1

I have a helper class called LeadHelper for the lead object and I am creating a test class called LeadHelperTest for it. Now the LeadHelper class calls other classes. After I run LeadHelperTest, the code coverager for LeadHelper and the classes it calls is above 75%. Now for release in Production do I need to create a separate test classes for each of those classes called by LeadHelper? Or is it enough just LeadHelperTest which calls other classes and their code coverage is also greater than 75%?

1 Answer 1

3

As long as you include LeadHelperTest in the change set (or whichever mechanism you're using for deployment), that is enough.