I need to make a process that sends out a chatter notification 1 week before a date on an account.
I only see options to run the process when a record is created or edited. How can I make it run when it is 1 week before the set date?
Salesforce Stack Exchange is a question and answer site for Salesforce administrators, implementation experts, developers and anybody in-between. It only takes a minute to sign up.
Sign up to join this communityI need to make a process that sends out a chatter notification 1 week before a date on an account.
I only see options to run the process when a record is created or edited. How can I make it run when it is 1 week before the set date?
I have not worked too much on Process Builder as yet, but I think the following should satisfy what you are looking for.
Advanced
", under that you have a checkbox
called "Do you want to execute the actions only when specified
changes are made to the record?
".Scheduled Actions
".7 Days
before Due Date
and also define the Chatter Post action.Scheduled Apex
that runs once per day and picks up all Accounts that have due date 7 days after the current date.