1

One of my users ran an import of leads into the system. When the import was complete she received this e-mail notification:

Your Leads import is complete. Here are your results: Leads Created: 89 Leads Updated: 500 Leads Failed: 294 (We couldn't import these due to errors.) Processed job information for imported Leads: No link is available because you do not have the correct permissions to manage Bulk Api jobs.

Can someone tell me what permission is required for her to receive the link to view the failed leads?

| improve this question | | | | |
2

Found it! The permission needed for this is the "Manage Data Integrations" on the user's profile.