2

In this example, let's say a new account is created and we want to have a kickoff lunch with that new account. I'm setting up my logic in process builder using a Start Date Time set to...

DATETIMEVALUE( Today() + 3 )

This will only yield today's date plus 3 days. How can I also ensure that it sets the time to noon?

1 Answer 1

2

Well you can use DATETIMEVALUE and pass Today and Time as Strings.

DATETIMEVALUE(TEXT(TODAY()) + ' 13:00:00')

If you are not in GMT, then things get bit complex. You might have to customize formula according to your timezone.