0

I'm having a process builder which creates a task whenever the stage is "Prospect". Now all is fine except due date field update. I'm setting "TODAY() + 7" in "Due Date Only" field in process builder. But this is not reflecting in the record.

enter image description here

3
  • 1
    what is being set on the record as the due date?
    – glls
    Apr 3, 2018 at 18:20
  • Empty Value !! @glls
    – 20182018
    Apr 4, 2018 at 6:05
  • what is the type of field Due Date Only ? are you sure you don't have other PBs that null out the value - check debug log
    – cropredy
    Apr 4, 2018 at 21:33

2 Answers 2

1

Try this. This has worked for me.

DATETIMEVALUE(TODAY()) + 7
0

Due date only is a sort of formula field, I believe. It takes the due datetime and pulls only the date. Populate the full due date (which is actually a datetime) and it should work.

You must log in to answer this question.

Not the answer you're looking for? Browse other questions tagged .