I am in the process of assessing Entitlement Processes and CaseMilestones.
I have set up an Entitlement Process that has 2 CaseMilestones set up.
- The first called First Response is initialised on Case creation.
- The second called Transferred is initialised on setting the Case Status to a certain value.
The Entitlement Process is set to exit on case close.
I have notices that the Transferred milestone will disappear from the Case Milestones related list when the case is closed, whereas the First Response milestone will not. Does anyone know why this might be the case?
In addition, the completion dates of the milestones are not being set when the case is closed. It was my understanding that all milestones would be marked as complete when the Entitlement Process exited. I have checked that the Entitlement Process is indeed exiting on close and this is the case. Does anyone know why the milestones are not getting completed?