0

I have some workflow and some process builder.

I want to know what is the execution order of process builder and workflow. I have some condition where I want my workflow to run first and then process builder, its working in all the condition except one where my process builder is working first and then workflow.

Can I control this behaviour?

9
  • 1
    Workflow executes first then process builder.
    – Ashwani
    Commented Dec 22, 2016 at 19:00
  • but in my case first process builder is working then workflow Commented Dec 22, 2016 at 19:01
  • Is workflow is written on parent object and process builder updates its child?
    – Ashwani
    Commented Dec 22, 2016 at 19:10
  • both are on same child object Commented Dec 22, 2016 at 19:11
  • 2
    I will suggest you to combine both action in same type. PB or workflow whichever suits you.
    – Ashwani
    Commented Dec 22, 2016 at 19:20

1 Answer 1

10

Order of execution of Triggers -> Workflows - > Process Builder.

Please see link and point number 12 and 13: Triggers and Order of Execution