How would I edit this formula to reflect a date of 10 days days after created date? It currently covers 48 hours or 2 business days.

CASE( MOD( DATEVALUE( CreatedDate ) - DATE( 1900, 1, 7 ), 7 ),
  0, CreatedDate + 1 + 2, /* Sun: CreatedDate + 1 wknd day + 2 days */
  4, CreatedDate + 2 + 2, /* Thurs: CreatedDate + 2 wknd days + 2 days */
  5, CreatedDate + 2 + 2, /* Fri: CreatedDate + 2 wknd days + 2 days */
  6, CreatedDate + 2 + 2, /* Sat: CreatedDate + 2 wknd days + 2 days */
  CreatedDate + 2 /* Default (Mon/Tue/Wed): CreatedDate + 2 days */
)

Thanks!!!

2 Answers 2

4

Since 10 business days are always 14 days (10 business days always include 2 weekends = 4 days), you can greatly simplify by using the following formula:

CreatedDate + 14   
1
  • Thanks Nicolas!! occam's razor: The simplest explanation is usually the correct one...
    – ShannonA
    Mar 31, 2016 at 14:20
0

Please use the following formula:

CreatedDate + /* 10 - number of Business days to add. Adjust in 2 lines below */ + MOD(10,5) + FLOOR( 10 / 5) * 7 + CASE( MOD( DATEVALUE( CreatedDate ) - DATE( 1900, 1, 7 ), 7 ), 0, 1, /* Sun: next Business day in 1 day */ 6, 2, /* Sat: next Business day in 2 days */ 0 /* is a Business day */ )