1

I am tring to update "end date" for current sprint in Agile Accelerator tool, but its giving me following error message.

FIELD_CUSTOM_VALIDATION_EXCEPTION

[object Object]: You can not change the end date after the sprint has started.

Thanks in advance.

  • Isn't the error message clear? If you started the sprint (per your word, "current", you have) then you may not change the end date. – Sebastian Kessel Jan 15 '16 at 6:25
  • Thanks for your reply. But due to some reason, we need to change end date of current sprint, so how can we do it? – user1037452 Jan 15 '16 at 6:30
  • I tried to update from backend , using query to 'agf__ADM_Sprint__c' table, still its not working. – user1037452 Jan 15 '16 at 6:34
  • I suggest you contact the makers of the managed package. If you can't remove the validation rule yourself, then you won't be able to update that value at all. I suggest you attempt to stop the current sprint first, either by changing data or by using the GUI. – Sebastian Kessel Jan 15 '16 at 7:12
0

Editing end/startdate of a current sprint is possible with a little patience

  1. Clone Sprint, save under different name
  2. Edit Start / End Dates as you need
  3. Move all work items to cloned sprint
  4. delete old sprint
  5. rename cloned sprint to old sprint name