There is a object Name "Opportunity" in which there is 4 fields mention below Closed Date, Month, Year, Quarter. Now As i fill the date manually , Once i click on "Save" the remaining field i.e 'Month', 'Year' and 'Quarter' should automatically populate For Eg: Closed Date: 23/02/2013 (Manually filled) then After Save : Month=Feb, Year: 2013, and Quarter: 1st. (should automatically filled)

Can anyone help me with this workflow rule or formula and how to do this??

0

1 Answer 1

3

You can create formula fields as follows

Month

MONTH(CloseDate)

Year

YEAR(CloseDate)

Quarter

FLOOR((MONTH(CloseDate)-1)/3) + 1